Client: Rober Bosch
Location: Šimanovci
Construction start date: 2012.
Construction end date: 2013.
Robert Bosch is building a factory near Belgrade in Šimanovci. The project includes 22,000 m2 land development around the halls, 11,000 m2 of roads and 5,000 m2 of parking, and about 2,500 m of drainage and sewerage, open retention for rainwater reception, entrance gate and fence with all the necessary equipment to control the entrance, and all the electrical work and lighting outside the building, telecommunications installation, electrical installation 1kW and 20kW power.
The works started on 01.11.2012. The deadline for completion is 01.07.2013.